KB-1369 Marking last 3 days of a month as non-working automatically marks the 1st, 2nd, or 3rd day of the same month

Symptoms

When using en_GB under internationalization settings, marking any of the last three days of any month as non-working day automatically marks the 1st, 2nd, or 3rd day of that month as non-working.

Cause

This issue has been reported to the Appian product team. The reference number for this issue is AN-41128.

Action

There are two available workarounds for this issue:

  • Store the non-working days in a constant instead of using a Process Calendar.
  • Set the non-working day when the system does not have en_GB set under internationalization settings:
  1. Log in as a System Administrator.
  2. Enable en_US.
  3. Make en_US the primary language.
  4. Sign out.
  5. Log in as a System Administrator.
  6. Mark the desired dates as non-working.
  7. Save the changes.
  8. Disable en_US and make en_GB the primary (if this is the requirement).
  9. Sign out.

Affected Versions

This article applies to all versions of Appian. 