Hi, When you configure an escalation for a task (ie. 2 days), does it look
garym
over 9 years ago
Hi,
When you configure an escalation for a task (ie. 2 days), does it look at the calendar and base it on working days only or is it just a straight 2 days from the time the task is initiated?
Thanks,
Gary
OriginalPostID-181188
OriginalPostID-181188
Discussion posts and replies are publicly visible
Parents
0
chetany
A Score Level 1
over 9 years ago
caladddays() would be appropriate. It will automatically take into account weekends and non working days. You can even pass the specific calendar you want to use. If you want it to be even more precise use caladdhours() which will exclude non-working hours also.
Cancel
Vote Up
0
Vote Down
Sign in to reply
Verify Answer
Cancel
Reply
0
chetany
A Score Level 1
over 9 years ago
caladddays() would be appropriate. It will automatically take into account weekends and non working days. You can even pass the specific calendar you want to use. If you want it to be even more precise use caladdhours() which will exclude non-working hours also.
Cancel
Vote Up
0
Vote Down
Sign in to reply
Verify Answer
Cancel
Children
No Data