hii all,
i have a interface to request for Range Reset in retail organization , once the required details filled user going to submit the form here , for each RANGE RESET i have set of tasks to complete , whenever user clicks submit button 12 tasks should assign to 4 owners along with the task completion time lines , task owners are
1.reset manger
2.assistant buyer
3.buye
4.merchandiser , how to achieve this , each should assign 3 tasks per head
Discussion posts and replies are publicly visible
Can you give us more details about the Tasks , can you share the current process model design .
Hello Ramesh Babu,You can do this in multiple ways. But I would ask what is the expected number of requests that would be created on a daily basis? What is the existing model that you are using. Are you trying to create tasks on Process-centric approach or Data centric approach? Do you want all the three tasks of each user to be created at once or are they going to be in a sequence?
This seems to be a pretty standard use case for processes. Task assignment and deadline calculation can be made dynamic. What exactly are you stuck with?
The provided information is not enough, Ramesh. Could you tell me what is the order of these taks? Are they parallel or sequential? What happens if a task owner is unable to complete them? Can they re-assign? Any other information you can help me with?
Rubbish
Spammy spam, oh so sly,Filling inboxes, oh my, my.Clickbait words and tricks they play,Trying to lead us all astray.
Spammy spam, we’ll delete you,No more tricks, we see right through.Unwanted emails, be gone far,Spammers, you won’t get too far.
Spammy spam, just a bother,Trying to sell what we don’t want, brother.We’ll report you, make you flee,No more spamming, let us be free.
Spammy spam, it’s no game,We won’t fall for your false claim.Respect our inbox, hear our plea,Spammers, now it's time to flee.
That's a nice Poem Stefan
i think tasks are sequential only , i will try to give some brief about my tasks , initially reset manger will fill the form and submits it after submission tasks should assign to each task owners
task1. reset manger will upload a file for scope details of the range reset in retail after this done
task 2 assistant buyer should have fill the raf form and submits
task 3 buyer will give initial approal to the raf send by the assistant buyer
task 4 after getting approval assistant buyer should add some more details and sends to merchandiser
task 5 merchandiser will upload a space recommendation plan and sends to buyer
task 6 buyer will approve the space recommendation plane by viewing that uploaded file
task 7 then agin the raf form will go to assistant along with the merchandiser uploaded file and the assistant buyer should confirms final draft of Raf
task 8 buyer will give final approval to raf received from the assist buyer
i have tasks like above mention , i have to show all the tasks to reset manger along with their statuses and i should show tasks assigned to task owners
how to achieve this