Hi Team,
I want to export more than 50 columns. Created a process to generate two excel and merge them
Case 1: If using to new doc in both smart services.
The combined doc is not started from specified cell. It starts from last data of first doc. E.g If first excel data ends at AV81 and other sheet starts from AW82, actually it should start from AW1.
Case 2: If I am updating the first doc then the data of 1st doc is not reflecting and only 2nd excel document data is reflected
Please let me know how to fix this.
Thanks
Discussion posts and replies are publicly visible
Hi Vikas,
Generally Export DSE to Excel will not allow you to export more than 50 column, if customer allows then offer them to split the data in multiple sheets, Else try using export Cdt to Excel ( depricated but still in use) or Export sql to excel which will help you to export required data.