Hi everyone,
One of the process models that I'm working on is using a Timer Event node, which is having a scheduled delay setting as shown below: (the constant returns 2 (integer))
I think the node supposes to delay for 2 minutes, then will activate the next node (Merge document) to run.
However, this Delay node has stuck there for much longer than 2 minutes, and when I check Process History, the node is Cancel.
The Merge Document node does not have any setting for Scheduling either
I haven't worked with Timer Event before, and couldn't find the reason for this behaviour from documentation. Could anyone help me with this?
Thanks a lot,
Discussion posts and replies are publicly visible
Hi mollyn126,
So when you assign a timer event node after the given time ex:- 2min try to press refresh icon, by refreshing the process model while debugging it goes to the next node.
Hope this is helpful
I refreshed but it did not go to the next node...