Some or all of the following symptoms occur with the Process Calendar when using using en_GB under internationalization settings.
Marking any of the last three days of any month as a non-working day automatically marks the 1st, 2nd, or 3rd day of that month as non-working.
Changing the working hours of any of the last three days of any month updates the 1st, 2nd, or 3rd day of the month instead. Changes to the working hours of any of the last three days of a month are not updated.
This issue has been reported to the Appian product team. The reference number for this issue is AN-41128.
There are two available workarounds for this issue:
This article applies to all versions of Appian.
Last Reviewed: March 2019