Hello Appian,
I want to end the process automatically, if no work is going on for an hour after the process start.
I thought "deadline" would play such role in the process model, but the process continues even after I set the one hour deadline.
Please let me know if there is a way to end the process automatically, after no work is going on for an hour after the process start.
Or if the deadline is the right way, I may have done something wrong with the setting, so please give example to follow.
Thank you in advance.
Discussion posts and replies are publicly visible
Hi Dreamwise,In PM you can add timer event to User Task in exception configuration and configure the time to end process automatically after certain time.Ex:
Thank you All, it was very helpful.
I got it solved!!