Are there any recommendations, tips, literature available for Sizing the requirements for Appian development ?
For other BPM platforms there are sizing sheets (Tool) available .
Discussion posts and replies are publicly visible
Hi,
Found this resource: https://community.appian.com/success/management/w/program-management/2164/project-sizing-and-estimation
As per my own experience, we estimate based on the assignees level of expertise and comfort on the changes required in a user story.
Other than that, if the changes are very simple and would not require extensive testing, then we provide estimation of 1-3 days. If the changes are of medium complexity and would need to be tested thoroughly, we generally provide estimate of 1-2 weeks. If the changes are complex, would require extensive analysis on backward compatibility and rigorous testing the estimation would be for 3-4 weeks.
Hope this helps!
For Simple what are the number of Workflow activities , integration points ?