I have created a MNI in a user Input task
In the assignment Tab, set the assignment to one to one as well
The above group contains two users. But as soon as one user completes the task, whatever the data filled by that user is showing to the other user as well.
Could you please help me to resolve this error
Discussion posts and replies are publicly visible
Hi Mike, thanks for the suggestion. I have already tried with this. Please refer the below screenshots.
In the ACP
Data in PV after 1st Instance
In second Task, I put these details
After submitting the data,
I have made it multiple but still the data is not populated and it's replaced by new data.
Usually how if a task need to assigned to multiple users and collect their feedback how it is done. Is there any other way of doing this.
Thanks
You would need to save the form data in the Data Outputs tab in a way that can actually handle arrays. Your ACP would need to be single, whereas the PV it saves into would need to be Multiple. Then you should save the current instance's value, either appending it into the list, or saving it at a specific location in the array (assuming that works).
(or)
Please reference the attached sample application (23.1 export fyi) which successfully reproduces the individual-assignment-by-group-membership, and writes each individual user's text input (as well as their username and a timestamp) into an individual Map entry and appends it all to a list of map stored as a PV. After import and prior to running, you'll need to add one or more assignees to the "GMAT Assignees" group.
Group Multi-Assignment Test (23.1 export).zip
Configuration Preview
Task Form:
Data Output:
Result:
Hi Mike, thanks a lot for the answer. Now that the data is saved as map which gives more flexibility to extract it as well. Appreciated for your efforts.
Another function in Appian to specifically support your use case is this:
docs.appian.com/.../Process_Model_Recipes.html