Hi,
could someone explain me the answer of this question?
Q: One of the process models in your application takes 6 days to complete. You are considering reducing the days until a process archives after completion from 4 to 2. What percent of memory reduction for this process model would you expect to see after this change?
A: 20%
Discussion posts and replies are publicly visible
it is around 33% of memory reduction will happen
The correct answer is 20% but I don't know why. I thought 33% too.
Where is this question from? It makes no sense because it talks about two different parts of the process lifecycle. Active time and completed time. Changing the days before archive does not in any way change the time it takes to complete.
I found it into the "Senior Developer Certification Practice Test"