Hi All:
Quick question -- Just wanted to check is there a way we can change the process initiator from A to B user? We are doing a task re-assignment feature via records dashboard.
In our use case, there will be always one active task for a given record. We have given an option to to do "task re-assignment" for the user to reassign the task to themselves in the absence of person working on the task. The task re-assignment works perfectly, what happens next is, as the submits the form of the current task, the next chained task gets assigned to the old user (process initiator).
I know we can apply logic in the task assignment section, but just wanted to check is there is way we can change the process initiator as well. So it take cares for everything.
P.S. Currently, my task assignment configuration has process initiator.
Thank you!
OriginalPostID-264918
Discussion posts and replies are publicly visible
Parents
0
Stefan Helzle
A Score Level 3
over 8 years ago
The process initiator cannot be changed at all. If you want to use it for assignment and need to change it later, store it to a PV in one of the first nodes.
Cancel
Vote Up
0
Vote Down
Sign in to reply
Verify Answer
Cancel
Reply
0
Stefan Helzle
A Score Level 3
over 8 years ago
The process initiator cannot be changed at all. If you want to use it for assignment and need to change it later, store it to a PV in one of the first nodes.