Hi , based on process's needs we use expession "workdays()" withou
natasav
over 13 years ago
Hi , based on process's needs we use expession "workdays()" without definition of holiday days.
Definiotion of this function is as following:
workdays( input date, -constant).
The problem is that the result of this function in one moment was non working day in Appian Calendar, and the process trigers after 2 days.
Can you help me for redefining it?Do we need to specife all not working days in addtional constant?...
OriginalPostID-31322
OriginalPostID-31322
Discussion posts and replies are publicly visible
Parents
0
Sunny
Appian Employee
over 13 years ago
Thanks for bringing this issue to our attention. I was able to reproduce this issue. It seems that workdays function disregards any non-working day except weekends.
I have reported this issue to our technology team. Your reference number is: 46566.
If you are adding days to the start day, then you can use caladddays().
Cancel
Vote Up
0
Vote Down
Sign in to reply
Verify Answer
Cancel
Reply
0
Sunny
Appian Employee
over 13 years ago
Thanks for bringing this issue to our attention. I was able to reproduce this issue. It seems that workdays function disregards any non-working day except weekends.
I have reported this issue to our technology team. Your reference number is: 46566.
If you are adding days to the start day, then you can use caladddays().