We have 9 years process model which has few instances running currently on production. In which they have assigned tasks to one particular user who had left the organization now. How we can handle this one? 

    6 replies

    stefanhelzle0001
    Brainy
    Oct 30, 2023 10:20 AM UTC

    That is a business decision. I suggest to assign the tasks to another person.

    stewart.burchell
    Employee
    Oct 30, 2023 11:06 AM UTC

    I'd also encourage you to design into the process model an escalation path so that future tasks are not stranded in a similar way. Something like waiting for a period of time (e.g. 5 days), sending the assignee a reminder, then waiting 2 more days and then re-assigning to a manager's group - whatever makes sense for the organization that this is being used in.

    Known Participant
    Oct 30, 2023 11:09 AM UTC

    Escalation & exception won't work if the node is failing.