Activity chain not working as expected

Symptoms

User does not see subsequent task even when the tasks are activity chained.

The task is seen in the users tasks list instead.

Cause

The number of unattended nodes that exists between two (attended) activity-chained tasks surpasses the (default) maximum number of 50.

You can confirm if the number of nodes that exists between two (attended) activity-chained tasks 

Other reasons why an activity chain might break are in this documentation.

Action